On Wednesday, March 27 at approximately 20:35z, GOES-W (GOES-17) will undergo a yaw flip maneuver. During this maneuver, a data outage will occur for at least two hours for all Advanced Baseline Imager (ABI) channels. Some channels may take up to 8 hours to fully come back online. Additionally, the space weather sensors and GLM sensors will be affected.
What is a yaw flip?
The yaw flip is important because it helps mitigate the Loop Heat Pipe (LHP) heat-dissipation issue with the GOES-W ABI. According to GOES-R Product Quality Engineer, Dave Pogorzala, during this time of year the amount of sunlight shining on the ABI begins to increase due to the orientation of the ABI in relation to the sun and the earth’s tilt. This causes increased saturation of the ABI IR channels due to the LHP. Flipping the ABI upside down helps to mitigate the increased sunlight effects because some of the components on the satellite act to physically shade the ABI sensor. This shading effect is maintained until the sun/earth/satellite orientation changes again near the autumnal equinox.
Figure 1 below shows the current orientation of the GOES-W satellite on the left and the new orientation after the yaw flip on the right.

What should I expect?
The GOES-W yaw flip will begin at approximately 20:35z on March 27. There will be a data outage of all ABI channels for at least two hours. After that, channels 1 to 6 will return quickly. However, channels 7 to 16 will return gradually, with some taking up to an additional 6 hours to fully return.
Questions?
We want to hear from you! If you have any questions or concerns, contact the TOWR-S team through NWS Chat by joining the "towr-s" group.
- 2023 Satellite Operation Communications
- 2022 Satellite Operation Communications
- 2021 Satellite Operation Communications
- 2020 Satellite Operation Communications
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Bands 11 & 15 [October 15, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Band 9 [October 13, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Bands 8, 10, 12 & 16 [October 9, 2020]
- GOES-17 ABI Loop Heat Pipe Anomaly Fall Season Preview [October 7, 2020]
- GOES-17 Loop Heat Pipe Anomaly Summer Season Concludes [September 1, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES ABI Bands 13 & 14 [August 26, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES ABI Band 15 [August 14, 2020]
- GOES-17 Mode 3 Cooling Timeline Operations [August 10, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES ABI Band 11 [August 10, 2020]
- GOES-17 Loop Heat Pipe Anomaly Impacts Update [August 4, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Band 8 [July 30, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Band 10 [July 29, 2020]
- Loop Heat Pipe Anomaly Impacts on GOES-17 ABI Bands 12 & 16 [July 24, 2020]
- GOES-17 Cooling System Impacts Update [July 22, 2020]
- GOES-17 Mode 3 Cooling Timeline Operations [April 3, 2020]
- GOES-17 Cooling System Impacts Update [April 3, 2020]
- Upcoming Deactivation of GOES-15 Operations and Products [February 27, 2020]
- GOES-W Scan Strategy Testing [February 18, 2020]
- GOES-17 Cooling System Impacts Update [February 5, 2020]
- 2019 Satellite Operation Communications
- GOES-W Scan Strategy Testing [December 9, 2019]
- Mode 6: GOES-E/W ABI Operational Flex Mode Transition to 10 Minute Cycle [March 29, 2019]
- GOES-W Yaw Flip Data Outage [March 27, 2019]
- GOES-R Satellite Series: Upcoming ABI Mode 6 Testing [February 19, 2019]
- GOES-R Satellite Series Mode 6 Testing and GOES-17 Imagery Anomalies [February 7, 2019]
- GOES-17 ABI Mode 6 Testing [January 25, 2019]
- GOES-17 Cooling System Impacts Update [January 17, 2019]